Symptom
Scheduling WBS elements with set indicator 'Network scheduling' does
not adjust the dates of the WBS but considers them as restriction dates
for the activities of the networks.
Other Terms
Project planning board, restriction, WBS dates
Reason and Prerequisites
In Release 4.6, the logic has changed.
Solution
Advance development as modification:If you chose alternative network scheduling for project scheduling, the WBS dates are no longer considered as restriction dates for the activities.
Execute the specified source text changes, and include the following import parameter for function module CX_INIT_SCHEDULING:
Parameter name Reference type Proposal Optional Pass value I_FLG_NETZ_PSP CX_BOOL SPACE X X
In advance, consider Note 143439 as well as Note 134237 in Releases earlier than Release 4.5B.
SAP FI/CO Online Training - 21st Century Software Solutions
ReplyDeletewww.21cssindia.com/courses/sap-fi-co-online-training-40.html
SAP FICO Training , SAP FICO Online Training, SAP FICO Corporate Training, Best SAP FICO Training , Expert SAP FICO Training ,Best SAP FICO Online ... call us +919000444287 or contact@21cssindia.comsap abap training| sap advanced abap training| sap basis training| sap bo training| sap bods training| sap bw bi training| sap crm functional training| sap crm technical training| sap ehs training| sap fi co training| sap grc training| sap hana training| sap hr training| sap is training| sap mm training| sap netweaver training| sap oil gas training| sap pm training| sap pp training| sap qm training| sap sd training| sap security training| sap wm training| sap workflow training,
SAP FICO Training in chennai
ReplyDeleteWe provides Best FICO Training in Chennai with real time project assistance by our leading Financial Accounting and Controlling Consultant.
For Free Live Demo @ Call to 8122241286.
SAP MM, SAP SD, SAP HR,SAP FICO
www.thecreatingexperts.com
SAP FICO